Low-E coatings: soft coat vs hard coat for aluminium windows
A low-E coating controls the heat that would otherwise radiate across the cavity, and there are two ways to make it: the soft coat, deposited in a vacuum and the higher performer, and the hard coat, fired onto the glass as it is made and the more durable. The soft coat has to live inside the sealed cavity; the hard coat can face the weather. The schedule picks the coat by where it goes and what it has to do, not by a generic low-E line.
What low-E does
Glass radiates heat across the cavity: the warm pane radiates to the cool pane, and that is a real part of the heat path. A low-E coating is a thin metallic layer that reflects that long-wave radiation back, which is what lowers the U-factor. The coating is almost invisible, and the difference between the two types is how it is made and where it can be placed.
The soft coat
The soft coat is sputtered onto the glass in a vacuum, layer by layer, which lets it be tuned for a high performance — a low U-factor, and it can be combined with solar control in the same multilayer stack. It is mechanically delicate, which is why it is called soft, so it is always placed on a cavity face inside a sealed IGU, never on an exposed surface. On the standard sealed unit it is the coat that delivers the best numbers.

The hard coat
The hard coat is applied during the float process, so it is fired in and hard: it can be handled, cut and even left exposed. It is slightly lower in performance than the soft coat, but it survives the applications the soft coat cannot — single glazing, exposed faces and the lean build. Where the unit is not a sealed IGU, or where the coating has to face the weather, the hard coat is the specification.

The coating line, by climate
| Line | The cooling climate | The heating climate |
|---|---|---|
| The call | Cut the gain, keep the light | Hold the heat, keep the light |
| The coating | The solar line, the surface assigned | The infrared line, the surface assigned |
| The label number | The gain value, the market reads | The U value, the market reads |
| The schedule field | The coating, the surface, the build | The coating, the surface, the build |
Which coat, where
- Soft coat for the sealed double and triple IGU — the standard insulated unit, where the coat sits on a cavity face.
- Soft coat combined with solar control where the U-factor and the solar heat gain both have to be low in one stack.
- Hard coat for single glazing, heritage and lean builds where the coat cannot be sealed in a cavity.
- Hard coat where a coating has to face the weather, on a single-glazed or exposed-laminated build.
The coating, and which surface it sits on
The IGU has four surfaces, numbered from the outside in, and the coating sits on the surface the climate assigns: the cooling climate puts the line where the solar reflection works against the gain, the heating climate where the infrared reflection works against the loss. The surface number is on the glazing schedule — the coating, the surface, the build — and the label reads the whole unit, which is why the same coating on the wrong surface is a different number, and the schedule is where the surface is pinned.
The reading for the RFQ: the coating line is three fields — the coating, the surface and the build — and the three travel together. A coating call without the surface is a half line, and a surface without the build is the other half: the configured unit is what the label reports, and the three fields are what make the configuration stated, not assumed.
A worked example: one villa, two climates
The villa design is one — the same openings, the same proportions — and the schedule is drawn for two markets: the cooling-climate market where the gain is the enemy, and the heating-climate market where the loss is. The cooling version takes the coating line that holds the visible and cuts the infrared, the surface the cooling call assigns; the heating version takes the line that holds the infrared reflection, the surface the heating call assigns. The frames are the same, the glass build is the same family, and the coating line is the difference — the line the two labels report separately.
The worked reading at the label: the cooling label shows the gain number the market reads, the heating label shows the U number the market reads, and both labels are the same villa — the drawing is one, the schedule is two, and the coating line is the field the two share the shape of and split the value on. The order pack carries the two label sets, keyed to the market, per the RFQ.
Frequently Asked Questions
Can I tell the two apart?
Not by eye; both are essentially invisible. The data sheet names the coating and the face it sits on, which is the line the schedule reads.
Which gives the better U-value?
The soft coat, all else equal, because it is tuned in the vacuum deposition. The hard coat trades a little performance for durability.
Can a soft coat face outside?
No — it is delicate and is always placed on a cavity face inside the sealed unit. The hard coat is the one that can face the weather.
Does the coating survive the laminated build?
The coating sits on the surface the build assigns, and the laminate is built around it — the coating line and the interlayer line are independent on the same lite, and the reference covers the pair, per the schedule.
Is the hard coat the value option?
The hard coat is the line that takes the processing order the standard glazing runs, and the soft coat is the line that carries the higher performance at the build it needs. The schedule states which line the project takes, and the reference follows the line.